Construction Update

Construction Update –

Stage 1A works are expected to be complete by late February 2019.

After discussions today with our Construction partner, NE Civil, we have been provided with the following timeframe for Stage 1A works:

  • Remaining road capping on all roads to be completed by 15 February 2019
  • Road Base on all roads to be compacted and rolled to kerb height to be completed by 22 February 2019
  • Kerb and channel, and footpaths for all roads commencing 13 February 2019 and to be complete within 2 weeks
  • Power cable installation to commence  by 18 February 2019
  • Final layers of rock and laying of asphalt to all roads to be completed by 28 February 2019.

 

Stage 1B is expected to be completed 6 weeks after stage 1A and as such the indicative completion date is Mid April 2019. We will provide timeframes for subsequent stages once Stage 1A works are complete.

Share