Progress of the concrete works this week was slower than anticipated as some works did not pass Council inspection. This work has since been redone and is now ready for concrete pour next week.
The preparation works for footpaths is now complete along both the eastern and western sides of Adelong Boulevard. There is an expected 10-14 days of concrete works remaining for Stage 1A.